The Number: RM8.50 to RM89.64 Per Kilowatt

Malaysia’s penalty for data centres that reserve more electricity capacity than they actually use has risen roughly tenfold, to RM89.64 per kilowatt from RM8.50, according to Malaysia’s Ministry of Investment, Trade and Industry, as reported by The Star on November 11, 2026 and by data-centre industry outlet W.Media the following day. The charge in question is the Connected Load Charge (CLC) — a penalty Tenaga Nasional Berhad (TNB), the national utility, applies to medium- and high-voltage customers whose actual peak demand falls short of the capacity they reserved on the grid.

The increase is being framed by officials as a direct response to “phantom demand” — data centres and other large users reserving far more grid capacity than they draw, forcing TNB to build and hold transmission and generation headroom that sits idle. Investment, Trade and Industry Minister Johari Abdul Ghani has said Malaysia has approved 117 data centre projects with a combined maximum electricity demand of roughly 23,500 megawatts, according to W.Media’s November 12 report — a pipeline large enough that even a modest gap between reserved and used capacity translates into gigawatts of stranded planning.

What a Connected Load Charge Actually Penalizes

The CLC does not charge for electricity consumed. It charges for electricity reserved and not consumed, over a billing period that runs for six years from the date a customer’s supply connection is energised, according to W.Media’s reporting on the mechanism. A data centre operator that signs a grid agreement for 200 megawatts of capacity but draws only 100 megawatts in practice still pays the CLC on the unused 100 — a structure an Energy Commission finding cited by EdgeProp says matters nationally, because data centres across Malaysia are currently consuming less than half of their collectively declared electricity demand.

That gap is the policy problem the higher rate is designed to close. Reserved-but-idle capacity behaves, for grid-planning purposes, identically to real demand: TNB has to size transmission lines and generation contracts around the number an operator declares, not the number it eventually draws. A tenfold increase in the per-kilowatt penalty changes the arithmetic of over-declaring from a rounding error into a material cost line, at least for any operator whose actual utilisation lags its reservation by a wide margin.

The Admission Inside the Same Announcement: There Is No Fixed Rate

The detail that complicates the RM89.64 headline came from the same round of statements. Deputy Prime Minister and Energy Transition and Water Transformation Minister Fadillah Yusof, discussing the strengthened CLC, said there is no uniform charge applied to every data centre project — the actual cost a given operator pays is determined case by case, through technical assessment and the specific financing mechanism attached to its grid connection, according to reporting carried by The Vibes and Asia News Network.

That is a meaningfully different claim than “the penalty is RM89.64 per kilowatt.” A rate that varies by technical assessment is not a published tariff a prospective operator can look up and budget against; it is a negotiated or administratively determined figure that depends on inputs TNB and the Energy Commission have not disclosed a formula for. The RM89.64 figure being quoted across the coverage is best read as the ceiling case the ministry is prepared to describe publicly, not the rate every project should expect to be billed.

What a Data-Centre Operator Should Model Before Its Next Grid Agreement

The CLC increase did not arrive in isolation. On November 4, 2026, Malaysia’s Energy Commission moved to require new data-centre grid-connection applicants in Peninsular Malaysia to submit ten-year staggered demand projections and sign binding supply agreements with TNB, according to Malay Mail — replacing a process that had allowed operators to apply for bulk capacity allocations up front, according to the same report. Combined with the CLC increase, the direction of policy is consistent even where the specific numbers are not: Putrajaya wants data-centre operators committing to capacity figures they can defend, and wants a financial consequence attached when they cannot.

For an operator negotiating a new connection, or sitting on an existing reservation that runs well ahead of actual draw, the immediate problem is not the RM89.64 figure itself but the absence of a published formula behind it. Three things are worth doing before signing or renegotiating a grid agreement: ask TNB and the Energy Commission directly what CLC rate and billing basis apply to the specific project, in writing, rather than budgeting off a number reported from a ministerial statement; model exposure under the ten-year staggered projection framework rather than a single peak-year figure, since the connection agreement now locks in a multi-year demand trajectory; and revisit any existing reservation that sits meaningfully above actual draw, given that the Energy Commission has already flagged sub-50% utilisation as a sector-wide pattern it is monitoring.

Key takeaways

  • Malaysia’s Connected Load Charge, the penalty for reserving more grid capacity than a data centre actually uses, rose roughly tenfold to RM89.64 per kilowatt from RM8.50, per Ministry of Investment, Trade and Industry statements reported in November 2026.
  • The charge applies to the gap between an operator’s reserved capacity and its actual peak demand over a six-year billing period from connection, not to electricity consumed.
  • Deputy Prime Minister Fadillah Yusof has said no uniform rate applies to every project, since the actual charge is set through case-by-case technical assessment — meaning the RM89.64 figure in circulation is not a rate any specific operator is guaranteed to pay.
  • An Energy Commission finding says data centres nationally are consuming less than half their collectively declared electricity demand, the exact pattern the higher penalty is meant to discourage.
  • A separate November 4 rule now requires new grid-connection applicants to submit ten-year staggered demand projections and sign binding agreements with Tenaga Nasional Berhad, replacing bulk capacity allocations.